Monday, 29 October 2007

Schedule

Week 6 Complete rough animatic and start final storyboards.
Week 7 Progress Review on Tuesday, have all concept work ready. Draw out panels for animatic. Make any changes after review.
Week 8 Final animatic
Week 9 polish the animatic, and start a line test
Week 10 Time the inking and colouring process – make schedule for semester B
Week 11 Finish off any outstanding work. Sound effects/track.
Week 12 All pre-production work should be complete, ready to animate in week 13 onwards.
Christmas
Week 13 Start animating…
Week 14

No comments: